The following deliverables are related to the LEAPS-INNOV project:
Month 1-18 (Reporting Period 1)
No.
Title
Status
D10.1
POPD - Requirement No. 1
submitted
D1.2
Innovation Advisory Board ToR
submitted
D2.1
Conceptual Design Report for the germanium detector prototype system
submitted
D1.3
Report on Annual Meeting
submitted
D5.1
Collated existing solutions and future requirements of facilities for beamline synchronisation
submitted
D6.1
Summary report on design of the short period high field prototypes
submitted
D6.2
Summary report on design of advanced EPU prototypes
submitted
D6.3
Summary documentation of the two measurement bench prototypes
submitted
D7.1
Evaluation report on data rates and volumes and assessment of future needs of LEAPS facilities
submitted
D4.1
Design report of prototype gratings
submitted
D7.2
Report on metrics for data reduction and compression
submitted
D9.1
Co-Creation inventory / catalogue
submitted
Month 19-36 (Reporting Period 2)
No.
Title
Status
D2.2
Multi-channel integrated preamplifiers qualification
submitted
D4.2
Midterm report on EBL process: test sample realisation and fabrication path of full-sized prototype gratings
submitted
D4.3
Report on metrology
submitted
D5.2
Validation report on the design model of interferometry systems for online metrology
submitted
D5.3
Definition of a standard protocol for synchronisation between beamline components
submitted
D2.3
Preliminary qualification of the assembled detector head
submitted
D7.3
Report results on promising data reduction pipelines on datasets provided by LEAPS facilities and release as open-source to the community
submitted
D7.4
Best practices and guidelines for applying data reduction and compression at LEAPS facilities
submitted
D1.5
Report on Annual Meeting in month 36
submitted
D5.4
Definition of Europe-wide standard for fixed-target support for sample handling
submitted
Month 37-48 (Reporting Period 3)
No.
Title
Status
D4.4
Prototype gratings
submitted
D5.5
Validation of the performance of the magnetic levitation stage demonstrator
.
D6.4
Summary report on performance of the short period high field prototypes
.
D6.5
Summary report on performance of the advanced EPU prototypes
.
D3.3
Report on performance of candidate metrology techniques supporting manufacturing process of freeform optics
.
D4.5
Report on grating characterisation
.
D5.6
Integration of microfluidic chip with the contactless sample manipulation system
submitted
D1.7
Recommendations of RI-INNOV Coordination Group
submitted
D2.4
Detector prototype performances tests report
.
D6.7
Report on WP6 KT and TT best practise
submitted
D8.3
Report on outreach to European countries without LEAPS facilities
submitted
D8.4
Industry engagement in the context of instrumentation: worked case study booklet
.
D9.3
Recommendations to strengthen the LEAPS co-creation process
submitted
D3.4
Prototype mirrors with < 50 nrad rms slope errors
.
D4.6
Workshop on NeXtgrating technology
submitted
D5.7
Installation of the synchronisation protocol and demonstrator experiment at several facilities
.
D8.5
Final report on industry innovation activities and services provided to SMEs
.
D1.6
Report on Annual Meeting in month 48
submitted
D2.5
Evaluated production plan
.
D3.5
Systematic study of performance of different deterministic processing methods for X-ray reflective freeform optics
.
D5.8
Report on qualification of the metrology demonstrators
.
D8.6
Industry survey results & draft of long-term industry engagement strategy for LEAPS
.
D9.4
Co-creation science instrument pilots result and recommendations
.